The Feringa Building has found a contractor

The Feringa Building has found a contractor

The RUG has finally found a contractor for the technical infrastructure of the Feringa Building. On Wednesday, the university will sign the contract with De Groot-Lammerink Installatiecombinatie. They’ll start on the construction almost immediately.
12 February om 11:17 uur.
Laatst gewijzigd op 22 November 2020
om 16:19 uur.
February 12 at 11:17 AM.
Last modified on November 22, 2020
at 16:19 PM.
Avatar photo

Door Christien Boomsma

12 February om 11:17 uur.
Laatst gewijzigd op 22 November 2020
om 16:19 uur.
Avatar photo

By Christien Boomsma

February 12 at 11:17 AM.
Last modified on November 22, 2020
at 16:19 PM.
Avatar photo

Christien Boomsma

Christien is sinds 2016 achtergrondcoördinator bij UKrant. Ze plant de achtergrondverhalen en begeleidt de auteurs. Bij haar eigen verhalen ligt de focus op wetenschap en academisch leven. Daarnaast schrijft ze veel over onderwerpen als sociale veiligheid en maakt ze graag persoonlijke interviews. In haar vrije tijd schrijft ze jeugdboeken en geeft schrijftrainingen.

Almost a year ago, contracting for the job stalled as a judge intervened. UCE, a consortium made up of three companies, was in the running for the longest time. However, the RUG felt their offer of 90 million euros was too high and ended up employing a third party which offered to do the job for ten million less. UCE went to court, and the RUG was reprimanded. They shouldn’t have circumvented the tender process.

The new contract has finally been drawn up: De Groot-Lammerink will place all installations that are needed for the building’s climate regulation, water and electricity supply. The contractor will also perform maintenance on the building for the next ten years.

The holdup doesn’t seem to have led to any insurmountable issues. The construction and technical infrastructure need to be coordinated, but construction company Ballast Nedam won’t start ‘real’ construction until now. They have already installed two thousand piles. 

The RUG is not quite done yet. They still have to find someone to install three kilometres worth of lab tables, 450 fume hoods, and thirty laser labs.

Construction of the gas-free Feringa Building, which will be 62,000 square metres, has been happening in fits and starts. The tender process for the construction was halted in 2017 because the improving economy drove up prices. Ballast Nedam wasn’t hired until January 2018. The building is projected to be finished halfway through 2023. 

Dutch

12 February 2020 | 22-11-2020, 16:19
Array

De spelregels voor reageren: blijf on topic, geen herhalingen, geen URLs, geen haatspraak en beledigingen. / The rules for commenting: stay on topic, don't repeat yourself, no URLs, no hate speech or insults.

guest

0 Reacties
Most Voted
Newest Oldest
Inline Feedbacks
View all comments